Sarawak's Road Projects Under NKRA


One of the major Sarawak road projects approved under the NKRA initiative is the Kapit/Kanowit Road. This road is divided into 9 sections and 2 had been completed. 

JALAN SG. POI/NG. NGUNGUN
This 15.5 KM road starts from Sg. Poi and ends at Ng. Ngungun, joining the existing road. Construction works has commenced on 5th November 2012 and expected to be completed in 24 months

JALAN NG. NGEMAH/SRKTEMALAT
This 10 KM road which starts from Nanga Ngemah and ends at SK Ng. Temalat is awaiting approval from MOF/KKLW for the award of the contract

JALAN SG. YONG/KAPIT (PHASE 1)
Construction for this 1.1915 KM road had commenced on 1 February 2012 and the phusical progress is 60% which is on schedule

JALAN SG. YONG/KAPIT (PHASE 2)
This project involves the construction of about 9.6 KM road and a concrete bridge at Sg. Yong. Works had commenced in August 2012. The schedule completion date is February 2015

JAMBATAN SG. KANOWIT & APPROACH ROADS (2.6 KM)
Design for the project had been completed and now pending approval from the Federal Government to proceed with the tender. The estimated cost is RM52 million

JALAN SONG/SG. YONG (33.4 KM)
Design and documentation are ready and now pending approval from the Federal Government to proceed with the tender. The estimated cost is RM348 million

No comments:

Post a Comment

SARAWAK KOLOK MEE™ Recognised The Freedom Of Expression Is Essential For Any Society To Evolve Better.

Comments Are Welcomed But Will Be Moderated Depends On Situations.

Any Views Expressed Within SARAWAK KOLOK MEE™ Are Not Those Of The Author.